
Orion Minerals, Northern Cape base-metals developer, and the Industrial Development Corporation of South Africa, state financier, have moved their focus to project financing and concentrate offtake agreements after a July capital raise to advance the Prieska Copper Zinc Mine (PCZM). The package comprised a placement of ~289 million shares and conversion of loan amounts via ~233 million shares for about R67 million (US$3.73 million), alongside a share purchase plan targeting A$4 million (US$2.59 million). The SPP opened on July 15 and closes on August 5, 2025.  
Funding Plan and Use of Proceeds
Orion said roughly 522 million shares will be issued across the placement and loan conversions at 1.1 Australian cents per share, taking the total raise to about A$5.8 million (US$3.75 million). Eligible shareholders may apply for parcels up to A$30,000 (R355,000; ~US$19,754) at the same price. Proceeds will fund PCZM “Uppers” early works—principally dewatering and site activities—project optimisation, and working capital, while management pursues an offtake-linked financing structure.
Execution Timetable and Offtake
Following the March definitive feasibility studies (DFS) for both Prieska and Okiep’s Flat Mines, Orion’s near-term emphasis is to lock in offtake and debt for PCZM’s Phase 1 (Uppers) and progress execution in the September quarter. “Our pre-eminent agenda is achieving first concentrate production from Phase 1 (Uppers) at PCZM and dewatering the mine … Our goal is to have first concentrate production from the Uppers by Christmas 2026,” CEO Tony Lennox said. The company guides to first bulk concentrate 13 months after financial close, with Phase 2 (Deeps) concentrate 29 months later.
Project Scope and Costs
The 2025 Prieska DFS outlines a two-phase build designed to generate early cash flow from accessible upper-level ore while dewatering the historic workings to reach the long-life Deeps orebody. The study reported a post-tax NPV of A$568 million and IRR of 26.2% (8% discount rate) over a 13.2-year life of mine; capex to first concentrate in the Uppers is estimated at A$49 million (R560 million). Management is also running value-engineering and operational-readiness workstreams, including front-end engineering design, long-lead procurement and shaft dewatering.
Market and Policy Context
The funding push follows earlier pre-development facilities—R250 million from the IDC and a US$80 million precious-metals stream plus a A$10 million funding arrangement with Triple Flag Precious Metals—to underwrite trial mining and dewatering. Orion has reiterated that discussions with the IDC are continuing and that several potential offtakers are in advanced talks to underpin project debt. South Africa’s Mining Minister visited Prieska in May, with government positioning the Northern Cape as a copper hub within national industrial policy.
Industry Context and Pricing
Copper’s tariff-driven price dislocations in the U.S. market have eased after Washington limited planned import measures to semi-finished products, cutting the COMEX premium and refocusing attention on fundamentals. On the London Metal Exchange, three-month copper traded around the high-$9,000s per tonne in July; zinc hovered near $2,780–$2,800/t, supporting project economics but keeping capital discipline in focus for new builds.
Currency context and why multiple denominations appear
Amounts in Australian dollars (A$) reflect Orion’s primary equity-raising venue on the ASX (the share placement price and the share purchase plan are set in Australian cents), while South African rand ® figures relate to on-the-ground spend and local funding for Prieska in the Northern Cape (e.g., IDC facilities and site works are budgeted and paid in rand). US dollars (US$) are used where costs, financing instruments and future offtake are typically benchmarked to globally traded metals—copper and zinc are priced in US dollars, as are streams/royalties and many imported capital items. For comparability, any non-USD amounts previously shown alongside dollar equivalents were converted at prevailing spot rates on the day of writing; actual cash flows will follow the functional currency of each contract and may differ with FX moves between signing, drawdown and expenditure.
Company Background and Market Context
Orion aims to develop two complementary hubs: Prieska (copper–zinc) and the Okiep Copper Project (Flat Mines), both in South Africa’s Northern Cape. The company completed DFS work on both projects in March 2025 and has since concentrated on execution planning, financing and offtake. Orion says it will transition from an exploration-led company to an operator as Uppers is brought online, with the Deeps phase to follow after mine dewatering and shaft refurbishment.
Copper is a critical input for power grids, EVs and industrial equipment; zinc chiefly underpins galvanised steel. Prices have been volatile this year amid tariff headlines and shifting growth expectations, but both metals remain near multi-year averages. For Orion, offtake-linked debt and a phased build provide levers to navigate commodity swings while advancing a domestic supply source aligned with South Africa’s industrial plans.